Case StudyJanuary 18, 202610 min read

HBYS Migration: A Six-Week Process at a 120-Bed Hospital

From data migration to parallel running, from staff training to go-live — how do you plan a zero-downtime HBYS migration at a mid-sized hospital? We walk through a real case.

Burak DemirProduct Operations, TRtek
Case StudyBurak DemirProduct Operations, TRtek10

A 120-bed private hospital retired its 12-year-old HBYS (hospital information management system) and moved to a new one in six weeks. This article shares the weekly plan, the three critical problems encountered and the lessons we learned from them.

Starting conditions

  • Old HBYS: 12 years old, not updated for the last three years; 4 TB of data
  • Active users: 340 (physicians + nurses + accounting + administration)
  • Average daily outpatient volume: 1,200 patients
  • Goal: uninterrupted service, zero data loss, six weeks

Week 1 — Discovery and data inventory

Our technical team reverse-engineered and mapped the old database: 184 tables, 1.2 billion rows. The most critical discovery was that patient files were kept separately on the filesystem in the old system, with only path references in the database. That is why we rewrote two-fifths of the migration plan.

Lesson 1

Do not trust the old system’s documentation. Always extract the live schema with your own tools — losing two or three days saves the remaining five weeks.

Week 2 — Test environment and schema mapping

We moved a one-day snapshot of the old database into the new system’s test environment. We wrote a Python script for the mapping; 172 of the 184 tables matched automatically. The remaining 12 contained bespoke business logic — a 30-minute meeting with the clinical and administrative teams was enough for each of them.

Week 3 — Pilot department: outpatient clinic

Instead of migrating the whole hospital at once, we started with the outpatient clinic. Three specialities were selected: internal medicine, cardiology and orthopaedics. The old and new systems ran at the same time and staff worked with two screens. The first two days were chaotic; from day five everyone noticed they were working faster in the new system.

Week 4 — Inpatient and pharmacy

This was the critical week. Inpatient records were historically the messiest data set. During migration we noticed that medication administration records were missing for 218 patients — the old system had a bug and 3% of administrations had never been recorded. We reconstructed and filled those from pharmacy stock movements.

Lesson 2

Never schedule the inpatient module cut-over for a weekend. Having the physician present prevents the shock of a new interface on Monday morning.

Week 5 — Laboratory, radiology and financial modules

PACS and laboratory device integrations had to be rebuilt (14 devices in total). The old system used serial ports; the new one uses HL7 over TCP. Together with the biomedical team this was completed in three days. Parallel running of the accounting and SGK modules also started this week, so the month-end financial close could be produced from both systems.

Week 6 — Full go-live and decommissioning the old system

The final synchronisation was triggered at 22:00 on Friday and took three hours. At 09:00 on Saturday the old system was switched to read-only mode (10 years, as legally required for retention). On Monday everyone started their shift on the new system. In the first 24 hours the support line received 47 calls, all of them usage questions — there were no system errors.

What we feared most was data loss. Here is the picture after six weeks: we recovered 218 medication records that did not even exist in the old system. The new system made us retrospectively better.

Dr. Mehmet A., Deputy Chief Physician

The results in numbers

  • Zero hours of data loss, zero days of service interruption
  • Outpatient flow time 38% faster on average
  • SGK rejection rate fell from 8% to 1.2% in the first month
  • 4.2 hours saved per user per week (thanks to automation)
  • Support calls in the first month after go-live: 12 (all training-related)

In short

Three things never change in a successful HBYS migration: (1) independently verify the data inventory, (2) run in parallel with a pilot department, (3) keep an on-call rotation for 48 hours either side of the Friday evening cut-over.